Timeline varies drastically by product and certification route.
Step 1: Confirm Certification Route
Choose between KATS (Safety/EMC) and RRA (radio).Missing one route causes severe delays.
Step 2: Prepare Samples & Documents
·Samples: full functional units
·Documents: manual, circuit diagram, BOM, model difference statement
Preparation: 1–2 weeks (longer with repeated revisions)
Step 3: Laboratory Testing
·KC Safety: 2–4 weeks
·KC EMC: similar
·KC (RRA): 3–5 weeks (standard products)
Step 4: Review & Certification
·Mandatory Safety: review + factory inspection
·EMC / RRA: direct certification after review
Step 5: Certificate Validity & Maintenance
·Mandatory KC: 5-year validity with annual follow-up audit
·Voluntary / SDoC: 5-year validity, no annual inspection
Realistic Timeline
·Low-risk voluntary: 3–6 weeks
·Standard mandatory: 2–4 months
·Full radio + safety + EMC: 2–4 months+
Delays occur from testing failures and incomplete documents.