This guide uses real project experience to outline the actual timeline.
·Membership & VID: 1–2 weeks
·Document & sample prep: 2–3 weeks
·Pre-test: 1 week
·Formal lab test: 3–8 weeks
·USB-IF review & listing: 1–2 weeks
II. Typical Total Timelines
·Basic cable: ~8 weeks
·PD charger: 9–10 weeks
·USB4 2.0 device: ~12 weeks
III. How to Accelerate
·Parallel preparation
·Pre-certified components
·Pre-testing
·Avoid peak seasons
·Use QbS for derivatives